Article V. POST-DEVELOPMENT STORMWATER DISCHARGE  


500  The post-development stormwater discharge rate from an overall tract development of five acres or more proposing a fifteen per cent increase or 40,000 S.F. (whichever is less) in surface impermeability, shall not exceed the predevelopment rate of a 10-year, twenty-four-hour storm for all rainfalls up to a 25-year, twenty-four-hour storm.

(Ord. of 6-18-92)

501  Tract developments of two acres up to five acres proposing a thirty per cent increase or 30,000 S.F. (whichever is less) in surface impermeability, should have a post development discharge rate not to exceed the predevelopment rate of a 10-year, twenty-four-hour storm for the same storm event.

(Ord. of 6-18-92)

502  All other tract development shall be evaluated on a case-by-case basis depending on the impact of the proposed development to the stormwater drainage basin. The City's Authorized Agent will determine the requirements of developments under two acres.

(Ord. of 6-18-92)